FLOORPLANS & SCHEDULE OF ACCOMODATION
LEVEL | NIA SQ.M. | NIA SQ.FT. | |
---|---|---|---|
SIXTH | 408.2 | 4,394 | |
FIFTH | 403.1 | 4,339 | |
FOURTH | 1,630.1 | 17,546 | |
THIRD | 2,326.2 | 25,039 | |
SECOND | 2,327.4 | 25,052 | |
FIRST | 1,934.8 | 20,826 | |
GROUND | 1,774.4 | 19,099 | |
LOWER GROUND | 1,773.1 | 19,085 | |
BASEMENT B1 | 230 Bicycle Bays | ||
BASEMENT B2 | 37 showers, changing / locker rooms with 222 lockers and separate drying room | ||
Basement B3 | 50 car parking spaces | ||
DEVELOPMENT TEAM
Design and Build Contractor
P.J. Hegarty & Sons
Assigned Certifier
iGPT Certification Ltd.
Architect
Grafton Architects & OMP Architects
Planning Consultant
Tom Philips & Assocciates
Quantity Surveyor
Linesight
BREEAM Consultant
EASLAR & BDP
Structural & Civil Engineers
OCSC Consulting Engineers
Fire Safety Consultant
MSA
Mechanical & Electrical Engineers
Axis Engineering & BDP
Access Consultant
Maurice Johnson & Partners
Landscape Architects
Bernard Seymour Landscape Architects
PSDP Health & Safety
ARUP
Facade Consultant
Buro Happold
Architectural Visualisations
Modelworks
Project Managers
Lafferty Project Managers
Branding & Marketing
Originate.ie
SPECIFICATIONS




- Designed to be BREEAM Excellent and achieve A3 BER status
- Near Zero Energy Building
- Advanced chiller with integrated heat pump and PCM
- Solar control glazing and solar selective fins
- Embedded cooling coils in roof slabs
- LED lighting
- Designed to limit vampire electrical loads
- Groundwater recovery and low water use fittings
- Courtyard and roof landscaping to support local ecology
- Comprehensive facilities for walkers, runners, and cyclists